Data centers are getting their own natural gas power plants

Data centers are getting their own natural gas power plants

For IT leaders, the core issue is not power generation technology; it is whether speed-to-capacity justifies a long-lived operating constraint. Behind-the-meter gas can accelerate data center commissioning when grid interconnection delays threaten AI road maps, but it also converts an infrastructure bottleneck into a balance-sheet, compliance, and reputation commitment. What looks like a temporary bridge can become a durable dependency once capital is deployed and workloads are tied to that site.

This raises a governance question that many digital portfolios are not set up to answer clearly: who owns the decision rights for energy risk? If infrastructure, real estate, sustainability, and product leaders optimize separately, organizations can end up approving faster capacity that later increases regulatory exposure, emissions obligations, and community scrutiny. The xAI example shows that permitting and local stakeholder risk can become operational risk quickly, not just a communications problem.

There is also a portfolio trade-off. Self-generation may protect one program’s launch date, but it can increase total enterprise cost through fuel-price exposure, backup complexity, and future retrofits if the site later shifts to grid, storage, or renewable integration. CIOs and CTOs should treat this as a scenario-planning decision: what is the cost of delayed compute availability versus the cost of fossil lock-in over 10 to 20 years?

Practical next questions:

  • What is the enterprise threshold where delayed capacity is less damaging than long-term energy and compliance risk?
  • Who signs off on environmental, permitting, and community externalities alongside delivery milestones?
  • Can modular demand management, phased workload migration, or hybrid energy sourcing reduce time-to-power without locking the operating model into gas?

One of the biggest roadblocks to starting up a data center is getting approval to connect to the electric grid—a wait that could last as long as a decade. Some developers aren’t willing to wait and are instead opting to build their own off-grid, or behind-the-meter, gas power plants to fuel the AI boom.  

xAI’s Memphis campus has famously used dozens of natural gas turbines, some of them without permits, as far back as 2024. At the time, that facility was a rarity, and it faced scrutiny from regulators. It remains the subject of ongoing legal battles. But the strategy of going off-grid for power has since become a lot more common.

As of October 2026, data center developers have announced plans for more than 100 behind-the-meter gas power plants at facilities in the US, according to data from Cleanview, a market intelligence company. The facilities have a combined planned capacity of over 115 gigawatts, more than double the peak power demand of California. The vast majority of these announcements have come since the beginning of 2025.

It’s possible that not all these facilities will be built; only a small fraction are under construction or operating today. But there’s a growing trend of large data centers looking to build their own power supply, and this could shape the grid—and its climate impacts—for decades to come.

Building your own power plant is generally more expensive than just hooking up to the grid, but the AI rush has made developers willing to pay a significant premium to get online faster. “The biggest motivator for on-site power right now from data centers is speed,” says Musfika Mishi, an associate at BloombergNEF, an energy consultancy.

When developers want to build a new industrial facility—like a data center—that requires a lot of electricity, they need to request a grid connection from a local utility or regional grid operator. That request kicks off a yearslong process in which grid planners study the existing grid to understand what would need to be built to safely deliver power to the facility without compromising reliability. Upgrades might be required, like building new transmission lines or larger transformers, and the developer might be on the hook to help pay for them.

Rather than waiting for that process to play out, developers can opt to instead build their own power plants. These facilities are referred to as “behind the meter” because they sit on the customer’s side of a utility meter—supplying the building directly, rather than relying on a utility via a grid hookup.

“This shift in the data center developers’ power strategies towards off-grid gas raises some important questions about how data centers will be powered going forward,” says Brendan Pierpont, director of electricity at the think tank Energy Innovation.

Behind-the-meter doesn’t always mean being totally disconnected from the grid, however. Some facilities may build such plants as a temporary measure, eventually connecting to the grid and tapping their own power plants only as backup. “It’s really just a very expensive way to bridge that maybe five-to-seven-year timeline gap until these data centers can get a grid connection,” Pierpont says. 

Even if gas plants are pitched as a near-term solution, building new fossil fuel infrastructure could lead to longer-term effects, since an operator might choose to continue running plants once they’ve spent money building them. “Even though data centers say that it’s a grid-bridging solution, the probability that it is going to be in use much longer is a real risk, and that leads to fossil fuel lock-in,” Mishi says. 

The on-site gas rush could have major implications for greenhouse-gas emissions. Today, the US grid is still reliant on fossil fuels, but nuclear and renewables together make up about 40% of electricity generation. That means making a grid connection is generally a lower-emissions option than relying entirely on an on-site gas plant. (That’s not the case everywhere—India, for example, is expecting to see a data center boom in the next decade, and its grid is largely served by emissions-intensive coal-fired power plants today.) 

Utilities are already planning to build more natural gas power plants on the grid to meet rising electricity demand. Equipment manufacturers are struggling to keep up with the surge, and it’s pushing developers of behind-the-meter plants toward less-efficient alternatives. 

Today, large natural gas plants generally use combined-cycle turbines. These capture heat to generate additional electricity, making them more efficient than single-cycle turbines, which are generally cheaper to build. Very few of the planned behind-the-meter facilities, however, will use combined-cycle turbines, Mishi says. That means these off-grid plants will likely produce more greenhouse-gas emissions than even other natural gas resources. 

BloombergNEF is also tracking on-site natural gas plants at data centers, finding 181 gigawatts’ worth of announced projects globally, with 90% of that capacity designated for the US. If all planned behind-the-meter gas plants for data centers in the US go ahead, they could emit 345 million metric tons of carbon dioxide equivalent each year by 2035, according to a BloombergNEF report. That’s 152 million metric tons more than if those data centers pulled power from the US grid—a difference greater than the total annual emissions of the Netherlands. 

And while it might seem logical that data centers bringing their own power could ease communities’ energy bills, those facilities going off-grid doesn’t protect prices for everyone else, says Matthias Fripp, director of global policy research at Energy Innovation. More demand for natural gas could push its price higher, he explains, which could in turn raise rates for the roughly 60% of American households that use natural gas for heating and cooking. That effect may also trickle into electricity prices.

There’s still a lot of uncertainty about how much of this gas rush will come to fruition, so this future isn’t set in stone. Today, just 4.9 gigawatts of behind-the-meter gas projects tied to data centers are operating, and 15.8 gigawatts are under construction, according to Cleanview’s data.

Creative solutions could also help limit the climate burden of the on-site gas buildout, BloombergNEF’s Mishi says. Building gas alongside on-site renewables or energy storage could help limit how often a gas plant needs to fire up, she says, though the economics of building multiple energy sources can be tricky. 

While the grid is struggling to keep up with demand, building more renewables could help, Fripp adds. In a recent study, his team found that building renewables and energy storage to meet rising electricity demand could be reliable and cheaper than relying on fossil fuels.

“These data centers want a lot of power, and they want it fast, and the grid is not well equipped to provide that,” Fripp says. “There are potentially good solutions and bad solutions … Rushing off the grid and putting in your own behind-the-meter gas is probably a bad way, because it’s still going to raise other people’s bills, and it’s not great for the environment.”