6 Ways Cloud Migration Costs Go Off the Rails

More than 70% of companies have now migrated at least some workloads into the public cloud, according to Gartner research. This momentum will continue as companies plan to increase their cloud adoption in the wake of COVID-19. Yet even as enterprises embrace the many benefits of the cloud, managing the cost of cloud computing is an ongoing challenge.

Source: 6 Ways Cloud Migration Costs Go Off the Rails

. In fact, Gartner predicts that through 2024, 60% of infrastructure and operations (I&O) leaders will encounter public cloud cost overruns that negatively impact their on-premises budgets.

Here are the six common mistakes that cause cloud migration costs to go off the rails and the actions that I&O leaders can take to budget appropriately for cloud migrations. 

6 Ways Cloud Migration Costs Go off the Rails

Mistake No. 1: The wrong team

The choice of a migration partner is a critical component of a cloud migration strategy. Yet, many I&O leaders select a migration partner based on familiarity or low pricing rather than experience. Others try to save on partnership costs by giving the migration project to an internal team, even if they are not ready for it. Both of these choices often lead to mistakes and rework, increasing costs in the long run.

Mistake No. 2: The wrong emphasis

Under pressure to move quickly, I&O leaders often prioritize the “lift and shift” approach of moving workloads into the cloud without modifying them. For many on-premises applications, however, the best move for the business may be no move at all. 

The best move may be to rewrite and re-release an application in a cloud-native way, or even to replace it entirely with a SaaS-based alternative. Defaulting too quickly to a rehosting approach and deferring the cost to modernize or replace critical applications can result in higher cloud operating costs after migration.

Read more: 7 Workloads That Should Be Moved to Cloud Right Now

Mistake No. 3: Rushed application assessments

Advertisements
Advertisements
SaleBestseller No. 1
Samsonite Omni PC Hardside Expandable Luggage with Spinner Wheels, Checked-Medium 24-Inch, Teal
  • 24" SPINNER LUGGAGE maximizes your packing power...
  • PACKING Dimensions: 24” x 17.5” x 11.5”,...
  • 10 YEAR LIMITED WARRANTY: Samsonite products are...
  • MICRO-DIAMOND POLYCARBONATE texture is extremely...
  • SIDE-MOUNTED TSA LOCKS act to deter theft,...
SaleBestseller No. 2
Amazon Basics 24-Inch Hardside Spinner, Orange
  • 24-inch hardside spinner luggage for work travel,...
  • Reliable strength with extra-thick ABS hard shell,...
  • Easy to move with 4 double spinner wheels,...
  • Expandable for up to 15% more packing space;...
  • Product dimensions: 16.73 x 10.63 x 23.62 inches;...

The most critical early phase in a cloud migration project is application assessment, as it helps to determine which cloud migration approach should be used for each application. Failing to fully assess the workloads to be migrated is a common mistake, resulting in incomplete specification of migration requirements and downstream scope creep. 

If feasible, I&O leaders should ask their migration vendor to propose an initial cost at project start, but submit a revised statement of work and final price after the application assessment phase is complete. 

Mistake No. 4: Poor landing zone design

Failing to properly architect and implement the underlying cloud “landing zone” environments into which workloads are migrated can increase the costs of security and compliance. The landing zone setup should include designing account structures, federation to identity directories, virtual private cloud (VPC) networking, role-based access control (RBAC) roles and rule sets, and infrastructure for monitoring, security and configuration management. Ensure that the setup of these environments is considered well in advance of the migration and included in the scope of work. 

Mistake No. 5: Dependency bottlenecks

Another potential mistake that is often the result of an incomplete application assessment is the discovery of dependency bottlenecks. Failing to discover and account for the interdependencies between on-premises systems being moved can lead to incorrect grouping and ordering of application migrations, network performance issues and cascading delays. This can cause migrations to take more time than initially allotted, increasing costs. I&O leaders must map dependencies as part of the application assessment process to ensure appropriate migration timelines. 

Mistake No. 6: Hidden indirect costs

When budgeting for a cloud migration, I&O leaders often fail to consider indirect project costs, such as those associated with transforming their organization to operate effectively in the public cloud or the residual (sunk) costs of vacated data center capacity. These costs are frequently unavoidable, but are important to consider as a part of the holistic cloud migration budget.

New
artrips Checked Luggage 24 inch,Medium Suitcase with 8 Spinner Wheels,PC Lightweight Hardside Luggage with Cover Protector,Stripe Pattern Design,TSA Lock,Purple,55L
  • 【PC Hardside Light Weight Luggage&Size】Made of...
  • 【Large Packing Capacity】 artrips Hardside...
  • 【Safety】The TSA lock ensures the safety of the...
  • 【8 Silent 360°Spinner Wheels】 8 silent...
  • 【Checked Luggage with Stripe Pattern Design】...
New
GizmoSynth 24in Luggage Suitcase with Spinner Wheels, Expandable Travel Suitcase with Cup Holder & USB Port & Phone Holder
  • 【Convenient Front Opening Cover】The front open...
  • 【Built-in USB Port】The Travel Luggage Suitcase...
  • 【Multifunctional Holder Design】Carry-On...
  • 【With Lock & Anti Noise Wheel】Mounted...
  • 【Superb Durable Material】The suitcase ABS+PC...
New
FocusOnHome Luggage Set 4 pcs (20"/24"/29"/Travel Bag), PC+ABS Durable Lightweight Luggage with Collapsible Cup Holder, 360° Silent Spinner Wheels, TSA Lock, Gray
  • The four-piece luggage set includes a travel bag,...
  • The luggage is made of ABS+PC hard shell material,...
  • Luggage installed with TSA locks, convenient for...
  • Reinforced corners protect against impacts, so you...
  • Quiet 360° swivel silent wheels and 2-step...

Transformation costs to watch for include the cost to reskill existing teams, the cost to raise salaries to match market levels for cloud roles, changes to organizational structure and operating procedures, and the cost to adopt agile DevOps practices across the IT organization. Common residual costs from a cloud migration include losses in productivity due to vacated facilities and hardware, unused software licenses or unproductive staff. It can also involve the cost to run duplicate versions of the same system during a migration cutover period.

The post 6 Ways Cloud Migration Costs Go Off the Rails appeared first on Smarter With Gartner.